|
Construction
Law Notes
Edward J. Kinberg, Esq.
Melbourne, Florida
Change/Claim
Identification and Management Making Your Records Work for You
Introduction
Since retiring
from the Army, the majority of my practice has involved assisting
individuals and companies with construction and government contract
claims and disputes. While serving in the U.S. Army, the last half
of my duties were limited to representing the Army in contract claims
and disputes as well as various other contract matters. As such,
I have had numerous opportunities to analyze claims and defend or
prosecute contract disputes.
Over the years
I have seen a consistent "flaw" in most contractors change
and claims management programs. The most common flaw is simply lack
of attention. In the rush to complete a job, many contractors simply
over look obvious warnings or do not have a system in place to "flag"
developing problems. As a result, by the time an "problem"
hits my office, I, or experts I retain, are required to conduct
a time consuming and costly analysis.
Most contractors
have the tools in place to build a fairly simple and effective and
change/claim management system. By this point, many of you are probably
thinking "here's another claims person telling us to spend
more time and money on something that won't be much help,"
However, that is not the case.
If you currently
develop a cost and time estimates in preparing your bids and use
a basic spreadsheet program, you have the tools and knowledge in
place to develop and maintain an effective change/claim management
system. The only tools I use in analyzing a claim are contractor
provided data and Quattro Pro or Excel. I use both as my clients
tend to use one or the other, but any spreadsheet program will work.
Setting
up the System
Your claim/system
begins with the preparation of your estimate. In preparing your
claim you need to take the following steps:
Identify the
various activities that will be required and give each activity
a code number.
Determine a reasonable duration for performing the job. Once you
are awarded the contract, you will need to add the actual start
and finish dates for the activity.
List the labor hours (use hours and cost) required to complete the
activity.
List the materials required to perform the activity. You also need
to list the expected lead time to obtain the materials.
If shop drawings and submittals will be required, list the labor
hours and overall time expected for various shop drawings and submittals.
Many contractors do not do this, occasionally resulting in an unpleasant
surprise when they first realize the job is costing more than they
thought.
Since these are the basic steps most contractors go through in preparing
a bid, this should not require much extra effort.
Once the job
is awarded to you, you establish internal accounting codes to ensure
the time and cost for the job are accumulated in the same manner
as shown on your bid. While these codes may differ from the schedule
you provide the owner or prime contractor, they are essential if
you are to have an effective change/claim management system.
Your next step
will be to develop a change/claim management spreadsheet. You will
only need to develop this basic format once, as you will be able
to use it on other jobs. As you gain experience with the spreadsheet,
you will most likely modify and improve its use. The basic set up
for a change/claim management spreadsheet is shown below.
Insert
Attached Chart
You should,
of course, modify the column titles to meet the needs of your company
or a specific project. By using formula's to calculate a % relationship
between actual data and your estimate, you will be able to quickly
identify developing problem areas.
Using
the Data
The key to
success in using this system is regular entry of data and taking
prompt action when a problem area is discovered. On a short project,
this should be done at least once a week, on a longer project it
should be done once a month.
Identifying
a problem is simply the first step in effective change/claim management.
The next step is determining why you are having a problem. In this
regard, you need to consider the following possibilities:
The drawings
and specifications are defective.
Differing site conditions have caused an increase in cost.
Excess changes have interfered with your ability to perform the
work efficiently.
Various trades have come into conflict because of poor scheduling
or poor schedule control.
You have experienced unusual weather problems.
Delayed start of your portion of the work has caused an increase
in your costs.
Your suppliers are delivering critical items late or erratically.
You are having problems with your laborers.
You are having problems with your supervisors.
Your "blew" the bid.
Once you have identified the cause of the problem, you can then
take timely action to minimize/recover your losses. If the problem
is not your fault, you need to check the contract requirements for
the issue involved (change, delay, weather, failure of owner to
approve submittals in a timely manner, etc) and ensure you comply
with all contract requirements.
In order to
prevent a time consuming examination of the contract each time you
discover a problem, you should summarize the key change/claim provisions
in your contract and a establish a procedure for ensuring those
requirements are met. Your procedure should include provisions to
identify, establish and preserve documents that will be required
to support your position.
In the event
of changes, you need to establish a new activity code for each such
item, estimate the costs associated with the change and add the
item to your spreadsheet. By accumulating the costs according to
the new activity code, you will have an "instant" record
showing the actual cost of the change.
Conclusion
Effective change/claim
management cannot be achieved if you do not maintain and regularly
review your actual time and costs in comparison to your estimated
time and costs. While doing so requires an effective time/cost management
system, you do not have to spend a lot of time and money on such
a system.
By simply using
your bid as base line to compare against actual costs, you can quickly
and accurately identify problems before they get out of hand. While
you may have to put a more effort into your estimating in order
to develop the detailed breakdown you need for an effective change/claim
management system, you will also be improving the accuracy of your
bids.
The bottom
line in any construction project is time and money. As such, it
is essential that you implement an effective and simple system for
monitoring the time and money spent on a job. If you do not think
you can afford the time and/or money to do so, you cannot afford
to be in the construction business.
The information you obtain at
this site is not, nor is it intended to be, legal advice. You should
consult an attorney for individual advice regarding your own situation.
Home
| Practice Areas | Attorney
Profile | Articles | Web
Resources | Contact Info | Directions
© 2004 Kinberg & Associates All
rights reserved.
You may reproduce materials available at this site for your own
personal use and for non-commercial distribution.
All copies must include this copyright statement.
|