|
Construction
Law Notes
Edward J. Kinberg
Attorney and Counselor at Law
Edward J. Kinberg, P.A.
Melbourne, Florida
Introduction
It
Was Suppose to be Done When?
This month,
I will be reviewing a recent Illinois appellate decision discussing
the duty of a subcontractor or a subsubcontractor to perform in
a timely manner. If there are specific legal issues or cases, you
would like to see discussed in this column, please let us know.
The
Facts
In this case,
the owner of the building allowed a tenant to move in before the
occupancy date set in the prime contract. Unfortunately, the owner
and the prime contractor did not notify the subcontractor installing
exterior granite block (SC) or the subsubcontractor (SSC) responsible
for installing the sealant between the granite blocks.
Approximately
five months before the scheduled completion date (in the middle
of the winter), the tenant began to occupy the building. Shortly
after the tenant installed part of its computer system a water line
along an exterior wall broke causing approximately $1,000,000.00
in damage. Needless to say, the tenant (and its insurance company)
was not happy and sued everybody.
In its lawsuit,
the tenant, represented by the insurance company, claimed the SC
and SSC were responsible because the SSC had not sealed the granite
block, which allowed the water line to freeze.
While the SC
and SSC each admitted the area in question had not been sealed as
of the date the line froze, they claimed they were not responsible
for the following reasons.
Their contracts
did not call for them to complete the work for several months.
The owner and general contractor were aware of the defendant's progress
(or lack of progress).
They did not know any tenants were moving in early.
The SC and the SSC each filed a motion for summary judgment, which
was granted by the trial court. The tenant appealed the summary
judgment ruling, which resulted in the ruling discussed in the article.
In its appeal,
the tenant offered an additional "theory" for recovery
which was rejected by the Court for two reasons. First, there was
no evidence in the record to support the "new" theory.
Second, the Court found the "new" theory was not included
in the tenant's Complaint and that it could not be added on appeal.
The
Ruling
In a well written
decision, the Court denied the appeal. In essence, the Court found
that a subcontractor and its subcontractors are only required to
perform in accordance with the terms of the contract. Since the
contract did not require the work to be finished by the date in
issue, the owner allowed tenants to move in at its own risk.
The Court also
found that the SC and SSC were not responsible for knowing what
they were not told. In this regard, the Court noted that, while
there were a number of cases holding sub and subsubcontractors liable
for failing to perform in a workmanlike manner, that liability does
not come into being until the work is completed.
In its discussion
the Court noted it was being asked to "determine if these facts
impose a duty upon defendants to complete their work prior to (the
tenant's) undisclosed occupancy." In finding that it could
not impose such a duty the Court found that the SC cannot reasonably
be expected "of its own volition, to keep abreast of every
tenant's occupancy date and set its schedule accordingly."
In my opinion,
one of the most interesting aspects of this case was the fact that
the project architect sent a letter to the owner advising the building
was suitable for tenant occupancy a month before the water line
froze and six months before the required completion date. Unfortunately,
the Court's decision does not explain how the architect determined
the building was ready for occupancy without checking with the subcontractor
installing the exterior granite blocks.
Conclusion
If you are
a prime contractor, you need to ensure your subcontractors know,
and agree, to any performance acceleration. You also need to ensure
that your subcontractors pass that information on to their suppliers
and subcontractors.
If you are
a subcontractor, you need to ensure the prime is aware of your status.
While you do not have a duty to complete your work early, you do
have a duty to make adequate progress. In this case, one of the
primary factors protecting the SC and SSC from liability was the
Court's finding the prime was aware of their progress and knew the
exterior work had not been completed.
The information you obtain at
this site is not, nor is it intended to be, legal advice. You should
consult an attorney for individual advice regarding your own situation.
Home
| Practice Areas | Attorney
Profile | Articles | Web
Resources | Contact Info | Directions
© 2004 Kinberg & Associates All
rights reserved.
You may reproduce materials available at this site for your own
personal use and for non-commercial distribution.
All copies must include this copyright statement.
|